PNGRB CGD Amendment Regulations 2026: New PNG Pipeline, MLC Pipe and Safety Requirements

Department: Ministry of Petroleum and Natural GasAuthority: Petroleum and Natural Gas Regulatory BoardPublish: Applicable: 18-09-2026MinistriesMinistry of Petroleum and Natural Gas

Quick note

Below is the official summary and the reference document preview. Use “Open PDF” for full screen view.

Schedule a Call Back

IN +91

Summary

The Petroleum and Natural Gas Regulatory Board has changed some of the technical and safety rules that apply to City Gas Distribution networks in India.

The new rules were issued through the Petroleum and Natural Gas Regulatory Board (Technical Standards and Specifications including Safety Standards for City or Local Natural Gas Distribution Networks) Amendment Regulations, 2026, dated 18 September 2026.

The amendment does not rewrite the entire CGD framework. Instead, it changes selected provisions dealing with pipe materials, PNG service-line installations, use of Multi-Layered Composite pipes, pressure-regulating stations, existing LPG manifold pipelines and maintenance of thermoplastic pipes.

For CGD companies, contractors and engineering teams, the main task now is to identify which existing specifications, drawings, SOPs and field practices are affected by the revised wording.

The amendment is issued under the PNGRB Act, 2006 and further amends the 2008 CGD technical and safety regulations. It comes into force from the date of publication in the Official Gazette. 276594

PNGRB Amendment Regulations 2026 at a Glance

Particular Details
Issuing Authority Petroleum and Natural Gas Regulatory Board
Regulator PNGRB
Notification Date 18 September 2026
File Number PNGRB/Tech/1-T4SCGD/(4)/2023-Part(1) (E-6228)
Governing Law Petroleum and Natural Gas Regulatory Board Act, 2006
Principal Regulations PNGRB Technical Standards and Specifications including Safety Standards for City or Local Natural Gas Distribution Networks Regulations, 2008
Sector City Gas Distribution
Main Area PNG technical and safety standards
Schedules Amended Schedule 1A, Schedule 1D and Schedule 1E
Effective Date Date of publication in the Official Gazette
Separate Transition Period Not expressly specified
New Licence Requirement Not introduced by this amendment
New Fee Schedule Not prescribed
Main Technical Changes GI pipe use, copper tubing, MLC pipes, PE pipe restriction, DPRS/IPRS spacing, LPG-to-PNG pipeline use, squeeze-off rules

Regulatory Framework Behind the PNGRB CGD Technical Standards

A mix of authorisation conditions, technical standards, safety requirements and operating rules governs City Gas Distribution networks.

The technical framework relevant here comes from the PNGRB (Technical Standards and Specifications including Safety Standards for City or Local Natural Gas Distribution Networks) Regulations, 2008.

These regulations deal with the way CGD infrastructure is designed, installed, operated, and maintained.

The 2026 amendment changes three specific schedules.

Schedule 1A- Materials and Equipment

This schedule deals with materials used in the network and associated equipment.

The 2026 amendment changes the position relating to:

  • GI pipes
  • copper pipes and tubing
  • MLC pipes
  • PE pipes
  • meter-to-appliance connections
  • reinforced rubber hose

Schedule 1D- Design, Installation and Testing

This part covers engineering and installation-related matters.

The amendment changes:

  • DPRS/IPRS separation wording
  • steel-pipe design table
  • customer meter/regulator heading
  • use of existing LPG manifold pipelines for PNG supply

Schedule 1E- Distribution Piping Maintenance

This section now contains revised requirements on squeezing and reopening thermoplastic pipes.

These are targeted amendments. They do not replace the full 2008 technical framework.

Who Is Affected by the PNGRB Amendment Regulations 2026?

The biggest impact will be on organisations directly involved in CGD design, installation, operation and maintenance.

City Gas Distribution entities

CGD entities may need to examine whether their existing technical specifications still match the amended regulations.

Areas requiring attention may include:

  • material specifications
  • standard drawings
  • service-line design
  • meter connections
  • DPRS/IPRS layouts
  • maintenance SOPs
  • LPG-to-PNG conversion projects

Engineering and project teams

Design engineers need to pay particular attention to:

  • pipe material
  • location of copper tubing
  • MLC installation conditions
  • DPRS/IPRS separation
  • existing LPG manifold networks

Installation contractors

Field teams may need revised work instructions where older specifications are still being used.

Operations and maintenance teams

The squeeze-off changes directly affect maintenance practice.

Housing societies and residential complexes

This amendment is especially relevant where an existing reticulated LPG manifold pipeline is proposed to be used for PNG supply.

Material suppliers

Suppliers of GI pipes, copper tubing, MLC pipes and reinforced hoses may face more specific technical requirements in project specifications.

What Has Changed Under the PNGRB Amendment Regulations 2026?

The amendment touches several small but technically important areas.

The main changes are:

  • clearer use of GI pipes in above-ground service lines
  • location-based restrictions on copper tubing
  • recognition of MLC piping under prescribed standards
  • controlled use of MLC outside the kitchen and upstream of the consumer meter
  • restrictions on above-ground PE piping
  • specific meter-to-appliance connection options
  • revised 2-metre DPRS/IPRS separation wording
  • removal of the “pipelines on bridges” row from Table 2
  • express provision for using existing LPG manifold pipelines for PNG supply
  • marking and spacing requirements for thermoplastic pipe squeeze-off locations

The detailed amendments appear in Schedules 1A, 1D and 1E. 276594

Schedule-Wise Changes Under the 2026 Amendment

Schedule Area Main Change
Schedule 1A Materials and Equipment Pipe material, MLC, copper, PE, and appliance-connection requirements.
Schedule 1D Design, Installation and Testing DPRS/IPRS separation, bridge pipeline entry, meter heading and LPG manifold reuse.
Schedule 1E Distribution Piping Maintenance Squeeze-off marking and minimum spacing.

New Requirements for PNG Service Line Pipes and Tubing

GI Pipes in Above-Ground Service Lines

The amended provision says that Galvanized Iron pipes shall be used in above-ground service lines up to the consumer meter or meter control valve.

This gives project teams a clearer reference point for material selection.

The same provision also requires GI pipes and copper tubing to conform to the requirements given in Annexure IV of the standard.

Use of non-galvanised pipes is to be restricted as far as possible. Where they are used, they must be properly protected and painted. 276594

What this means in practice

Engineering and procurement teams should not look only at pipe diameter or pressure rating.

They also need to check:

  • type of pipe
  • location of installation
  • position in relation to the consumer meter
  • applicable Annexure IV requirements
  • corrosion protection where relevant

Copper Pipe and Tubing Requirements

Copper continues to be recognised, but the amended rule makes its location much more important.

For above-ground service lines, copper tubing after the consumer meter may be used in a manner that keeps it away from third-party access.

Before the consumer meter, copper pipe or tube should be used inside the kitchen only.

This is one of the most important details in the amendment because it prevents a broad reading that copper can be used anywhere upstream of the meter.

Why location matters

The amendment treats pipe use differently depending on whether it is:

  • upstream of the consumer meter
  • downstream of the consumer meter
  • inside the kitchen
  • outside the kitchen

That means the same material may not be acceptable in every location.

For field teams, installation drawings should clearly show this distinction.

PNGRB Requirements for Multi-Layered Composite Pipes in PNG Service Lines

Multi-Layered Composite pipes receive much clearer treatment under the 2026 amendment.

An MLC pipe can be used as an alternative to copper pipe or tube in the situations covered by the regulation, provided it meets the prescribed technical standard.

The amendment recognises MLC pipe conforming to:

  • ISO 17484-1
  • IS 17544

Where compliant MLC pipe is used upstream of the consumer meter and outside the kitchen, additional requirements apply.

In such cases, the relevant PNGRB Guidelines for Controlled Utilization of Multi-Layered Composite Piping Systems for above-ground PNG service lines must be followed.

These guidelines are linked with:

  • safe installation
  • prescribed installation methods
  • protection of the pipe
  • protection against third-party damage

Material compliance is only one part of the requirement

A pipe meeting ISO 17484-1 or IS 17544 is not automatically suitable for every location.

The installation conditions must also be checked.

A project team should therefore look at:

  1. whether the MLC pipe meets the prescribed standard
  2. where the pipe is being installed
  3. whether it is upstream or downstream of the meter
  4. whether it is inside or outside the kitchen
  5. whether the applicable PNGRB MLC guidelines apply

Can PE Pipes Be Used for Above-Ground PNG Service Lines?

The amended provision states that Polyethylene pipe shall not be used for above-ground gas pipes unless specifically permitted in the regulations. 276594

This should not be interpreted to mean that PE pipe is banned from the entire City Gas Distribution network.

The restriction here is specifically about above-ground gas piping.

Any underground application or other use must be assessed under the relevant part of the regulations.

What Pipes or Hoses Can Be Used Between the Consumer Meter and Gas Appliance?

The amendment also covers the short connection between the consumer meter set assembly and the consumer's gas appliance.

The permitted options mentioned are:

  • Galvanized Iron pipe
  • Copper tubing meeting Annexure IV requirements
  • steel-reinforced rubber hose

Where steel-reinforced rubber hose is used, it must conform to IS 9573 Part 2. 276594

What contractors should check

Before completing a consumer-side connection, the installer should check:

  • type of connection being used
  • compliance of copper tubing with Annexure IV, where relevant
  • compliance of reinforced rubber hose with IS 9573 Part 2
  • suitability of the connection for the approved installation

Technical Standards Referred to in the Amendment

Standard / Reference Related Area Relevance
ISO 17484-1 MLC pipe Technical conformity
IS 17544 MLC pipe Technical conformity
Annexure IV GI pipe and copper tubing Material requirements
IS 9573 Part 2 Steel-reinforced rubber hose Meter-to-appliance connection
PNGRB MLC Guidelines MLC piping outside kitchen/upstream of meter Installation and protection
PNGRB LPG-to-PNG Guidelines Existing LPG manifold system Safety and pipeline integrity

Reference to an IS standard should not automatically be treated as a new BIS registration requirement. The amendment itself does not create a separate BIS registration process for these materials.

Revised Safety Requirements for DPRS and IPRS Installations

The amendment also changes the wording around above-ground pressure-regulating stations.

A Distribution Pressure Regulating Station (DPRS) and an Individual Pressure Regulating Station (IPRS) are used to regulate gas pressure before it moves further through the distribution system.

For above-ground DPRS/IPRS installations:

  • security fencing is required according to local authority requirements
  • the distance between the DPRS/IPRS enclosure and the permanent wall of the nearest building or structure must not be less than 2 metres

What has actually changed?

Earlier wording referred to the distance between the fencing and the wall of the nearest building or structure.

The revised text specifically refers to the DPRS/IPRS enclosure and the permanent wall of the nearest building or structure.

That wording should be reflected correctly in technical drawings and layout reviews.

What Has Changed for Pipelines on Bridges?

Under the heading dealing with steel pipes, the fourth row of Table 2 – Design Factors for Steel Pipe Construction, relating to “Pipelines on bridges,” has been omitted. 276594

The notification does not say that pipelines on bridges are now prohibited.

It also does not explain within this amendment what alternative design factor should automatically apply.

For that reason, engineers should read the amended provision together with the principal regulations and any other applicable PNGRB technical requirements before making a design decision.

Change in Customer Meter and Regulator Installation Wording

One of the smaller amendments is a change in the heading dealing with customer meters and regulators.

The earlier wording:

Location for Customers' and Regulator Installations

is replaced by:

Location for Customers' Meter and Regulator Installations

This appears to be mainly a wording correction. The notification does not attach a separate technical condition to this particular heading change.

Can Existing LPG Manifold Pipelines Be Used for PNG Supply?

Yes, but the amendment does not provide unrestricted permission.

It specifically deals with existing:

  • carbon steel pipelines
  • mild steel pipelines
  • reticulated LPG manifold pipeline systems

used in:

  • housing societies
  • residential complexes

Where such an existing LPG manifold pipeline is proposed to be used for PNG supply, the relevant PNGRB guidelines must be followed to ensure the safety and integrity of the pipeline system. 276594

This does not mean every LPG system can automatically be converted

An existing LPG manifold system may have been designed and operated under different conditions.

Before it is used for PNG, its suitability has to be considered within the framework referred to by PNGRB.

The amendment therefore creates a regulated route for the use of existing infrastructure rather than a blanket approval.

What Housing Societies Should Check Before LPG-to-PNG Conversion

Housing societies considering a shift from an existing reticulated LPG arrangement to PNG should first coordinate with the authorised CGD entity.

Requirement expressly referred to in the amendment

The applicable PNGRB guideline for use of existing LPG manifold pipelines for PNG supply must be followed.

Practical checks that may be required

Depending on the installation, the technical team may need to review:

  • pipeline material
  • age and condition
  • visible corrosion
  • pipe routing
  • joints and fittings
  • valves
  • previous maintenance records
  • available drawings
  • pressure suitability
  • accessibility
  • integrity of the overall system

These checks are practical implementation considerations. The amendment itself does not set out this exact checklist.

New Squeeze-Off and Reopening Rules for Thermoplastic Pipes

A squeeze-off is a maintenance method used to temporarily stop or control gas flow in certain thermoplastic pipes by compressing the pipe.

The 2026 amendment introduces clearer restrictions on what happens after such a location has been reopened.

Three rules stand out:

  1. The place where squeezing and reopening has already been carried out must be properly marked.
  2. The reopened pipe cannot be squeezed again at the same location.
  3. There must be at least 1 metre between consecutive squeeze-off locations.

Why the marking requirement matters

A maintenance crew may return to the same pipeline after months or years.

If the earlier squeeze-off point is not identified, the same section of pipe could be selected again.

The amended rule removes that ambiguity by requiring proper marking.

Key Technical Values Under the 2026 Amendment

Requirement Technical Value / Standard
DPRS/IPRS separation Minimum 2 metres
Consecutive squeeze-off locations Minimum 1 metre
MLC pipe ISO 17484-1 or IS 17544
Steel-reinforced rubber hose IS 9573 Part 2
GI and copper requirements Annexure IV

Material-Wise Requirements for PNG Service Lines

Material Where It Is Relevant Technical Requirement Main Limitation
GI pipe Above-ground service line up to consumer meter/control valve Annexure IV Use according to prescribed application
Copper tubing Before/after meter in specified situations Annexure IV Location-based restrictions
MLC pipe Alternative to copper in permitted situations ISO 17484-1 or IS 17544 PNGRB guideline conditions where applicable
PE pipe Above-ground gas piping Only where specifically permitted General above-ground use restricted
Steel-reinforced rubber hose Meter-to-appliance connection IS 9573 Part 2 Must conform to prescribed standard

Old vs New PNGRB CGD Technical Requirements

Compliance Area Earlier Position 2026 Position Business Meaning
GI pipe Earlier provisions covered service piping GI use up to consumer meter/control valve is expressly stated Material specifications should be reviewed
Copper pipe Earlier treatment was broader Location before the meter is restricted Drawings and installation practice matter
MLC pipe Earlier position not fully reproduced in amendment MLC recognised with specified standards and conditions Additional design option with safeguards
DPRS/IPRS Distance wording referred to fencing New wording refers to enclosure and permanent wall Layout measurement point is clearer
Pipeline on bridges Specific table row existed Row deleted Engineering interpretation requires care
LPG manifold system Earlier wording did not contain the new express provision Existing CS/MS LPG manifold systems addressed for PNG use Residential conversion projects need guideline-based review
Squeeze-off Earlier entries replaced Marking, no repeat squeeze at same point and 1 m distance specified Maintenance SOPs need review

When Do the PNGRB Amendment Regulations 2026 Come Into Force?

The regulations come into force on the date of publication in the Official Gazette. 276594

There is no separate future commencement date mentioned in the amendment text.

Is There a Transition Period?

The notification does not expressly provide a separate transition period.

Businesses should therefore avoid assuming that a general grace period of three months, six months, or any other duration is available.

If PNGRB later issues a separate clarification or implementation direction, that document would need to be considered independently.

Do Existing PNG Pipelines Need to Be Replaced?

The notification does not say that every existing PNG pipeline must be replaced.

That distinction is important.

A technical amendment may require a company to review an installation without automatically requiring physical replacement.

CGD entities should check:

  • whether the existing installation falls within the amended provision
  • whether the installation predates the amended wording
  • whether separate PNGRB guidelines apply
  • whether an engineering integrity review is required
  • whether the project is existing, ongoing or new

A blanket replacement statement would go beyond what this notification says.

Does the Amendment Introduce a New Licence or Registration?

These technical amendments create no new licence or registration process.

The notification deals with technical standards, installation, material selection, and maintenance.

Any existing PNGRB authorisation requirement continues to be governed by the relevant legal framework separately.

Does the Amendment Introduce New Fees or Penalties?

The amendment itself does not prescribe a new fee schedule or a specific penalty amount for these changes.

Businesses should therefore not treat this notification as a new fee or penalty notification.

Any enforcement consequence would need to be examined under the applicable parent law, regulations or authorisation conditions.

Impact on City Gas Distribution Companies

Engineering and Design

Engineering teams are likely to carry the heaviest implementation responsibility.

Existing design documents may need to be checked for:

  • service-line material
  • copper pipe location
  • MLC use
  • DPRS/IPRS separation
  • meter connection design
  • LPG manifold conversion

Procurement

Procurement teams should ensure that technical purchase specifications match the amended requirements.

This may involve checking:

  • Annexure IV requirements
  • ISO 17484-1
  • IS 17544
  • IS 9573 Part 2

Construction and Installation

Contractors working from older drawings or specifications may need updated instructions.

This is particularly relevant where:

  • copper is used upstream of a meter
  • MLC pipe is installed outside a kitchen
  • a DPRS/IPRS is being positioned
  • an existing LPG pipeline is being reused

Maintenance

The squeeze-off amendment has a direct impact on field maintenance.

Teams should ensure that:

  • previous squeeze locations are marked
  • the same reopened point is not squeezed again
  • one metre is maintained between consecutive squeeze-off locations

Existing Residential Networks

Residential projects with older LPG manifold systems deserve separate attention because the amendment now expressly recognises their possible use for PNG subject to PNGRB guidelines.

Impact on Housing Societies and Residential Complexes

Housing societies may benefit where existing LPG infrastructure can be safely retained for PNG use, but this should not be treated as a simple infrastructure reuse decision.

The authorised CGD entity may need to assess:

  • condition of the existing pipeline
  • material
  • safety
  • integrity
  • suitability for PNG service
  • compliance with the relevant PNGRB guideline

For societies, the practical benefit is that existing infrastructure may be considered rather than automatically discarded, provided the applicable technical requirements are met.

Impact on PNG Contractors and Installation Agencies

Contractors should pay close attention to site-specific requirements.

A drawing that was technically acceptable under an earlier specification may need to be rechecked if it involves:

  • copper upstream of the meter
  • MLC piping
  • above-ground PE piping
  • consumer-appliance hose
  • DPRS/IPRS location
  • existing LPG pipelines

Site supervisors should also make sure that older work instructions are not being used without review.

Impact on Pipe, Tubing and Gas Equipment Suppliers

Suppliers may see tighter technical specifications in tenders and procurement orders issued by CGD entities.

Products most directly affected include:

  • GI pipes
  • copper tubing
  • MLC pipes
  • steel-reinforced rubber hoses

Suppliers should be ready to provide technical data showing conformity with the relevant standard where required.

The notification, however, does not itself create a new standalone product registration process.

What CGD Operators Should Review in Existing Projects

Existing projects should not be ignored simply because construction has already started.

A structured review can cover:

Drawings

Check whether the pipeline route and material remain consistent with the amended position.

Approved material list

Confirm whether the selected pipe or hose still fits the application.

MLC installations

Check both material conformity and installation location.

Copper installations

Confirm whether copper use before the meter is within the permitted location.

DPRS/IPRS

Recheck enclosure-to-wall distance.

LPG manifold systems

Identify any residential project using an existing LPG pipeline for PNG.

Maintenance records

Make sure squeeze-off locations can be identified.

What Should Be Checked Before Starting New PNG Installations?

Before construction starts, project teams should verify:

  • approved pipe material
  • meter position
  • copper pipe location
  • MLC standard
  • MLC installation safeguards
  • PE pipe restriction
  • meter-to-appliance connection
  • DPRS/IPRS separation
  • LPG-to-PNG conversion conditions
  • maintenance-related design considerations

This early review can reduce the need for design changes after installation has already begun.

PNGRB 2026 Compliance Checklist for CGD Entities

Review Area What Should Be Checked Nature
GI pipe Use up to consumer meter/control valve Regulatory requirement
Copper pipe Location before and after meter Regulatory requirement
MLC pipe ISO 17484-1 or IS 17544 Regulatory requirement
MLC installation PNGRB guideline where applicable Regulatory requirement
PE pipe Above-ground restriction Regulatory requirement
Meter connection Permitted pipe/hose option Regulatory requirement
Rubber hose IS 9573 Part 2 Regulatory requirement
DPRS/IPRS Minimum 2 m distance Regulatory requirement
LPG manifold reuse Applicable PNGRB guideline Regulatory requirement
Squeeze-off marking Previous location identified Regulatory requirement
Squeeze spacing Minimum 1 m Regulatory requirement
Drawings Review against amendment Recommended internal control
SOPs Update where needed Recommended internal control

Technical and Operational Risks to Avoid

The amendment highlights several areas where an incorrect interpretation can create compliance problems.

Businesses should avoid:

  • using the same pipe material across all locations without checking the rule
  • assuming copper may be used anywhere upstream of the consumer meter
  • selecting MLC pipe only on the basis of material certification
  • ignoring MLC installation safeguards
  • using PE pipe above ground without confirming that the regulations permit it
  • measuring DPRS/IPRS spacing from the wrong reference point
  • assuming an existing LPG pipeline is automatically suitable for PNG
  • squeezing the same reopened thermoplastic pipe location again
  • failing to mark a previous squeeze-off point
  • ignoring the one-metre minimum distance

Potential Benefits of the 2026 Amendment

The amendment can make technical decisions easier where earlier wording left room for interpretation.

Possible benefits include:

Better material clarity

GI, copper, MLC and PE now have clearer location-based treatment.

More controlled MLC use

The rule recognises MLC but also ties it to technical standards and installation safeguards.

More precise DPRS/IPRS layout requirements

The revised wording gives a clearer reference point for the two-metre distance.

Safer maintenance practices

The squeeze-off provision reduces the risk of repeated work at the same point.

Better use of existing infrastructure

Housing societies may be able to use existing LPG manifold systems for PNG where safety and integrity conditions are met.

Implementation Challenges for CGD Operators

The main challenge is likely to be coordination across departments.

A technical amendment may look small on paper, but it can affect:

  • drawings
  • procurement
  • contractor instructions
  • material approvals
  • site inspections
  • maintenance manuals
  • residential conversion plans

Large CGD companies may already have hundreds of approved drawings and standard specifications in circulation.

The practical task is therefore to identify exactly which ones need revision rather than changing every document unnecessarily.

Business and Regulatory Perspective

The 2026 amendment does not add a new layer of licensing.

Its focus is more technical.

PNGRB is tightening or clarifying how certain materials and installations should be handled across the CGD network.

For businesses, the bigger risk is not missing a new application form. It is continuing to use an old engineering specification after the technical rule has changed.

That is why engineering, procurement, compliance and field teams need to read the amendment together rather than treating it as a legal-team-only update.

What Businesses Should Do Next

A sensible review can be carried out in the following order:

1. Map the affected projects

Identify new, ongoing and existing projects involving the amended provisions.

2. Compare current specifications

Check current standard specifications against the revised Schedule 1A, 1D, and 1E requirements.

3. Review drawings

Focus on copper, MLC, DPRS/IPRS, and existing LPG manifold infrastructure.

4. Check procurement documents

Make sure material descriptions refer to the correct standards.

5. Review contractor SOPs

Remove outdated instructions where necessary.

6. Update maintenance practice

Include squeeze-off marking and one-metre spacing.

7. Maintain review records

Keep a record of the technical and regulatory review carried out.

8. Monitor related PNGRB guidelines

Some provisions, especially MLC and LPG-to-PNG use, depend on separate PNGRB guidelines referred to in the amendment.

How Corpseed Can Help with PNGRB and CGD Regulatory Compliance

The difficult part of a technical notification is often not reading the amendment itself. The challenge is understanding which part applies to a particular project, installation, or business activity.

Corpseed can support CGD companies, contractors and other affected businesses through regulatory compliance services such as:

  • PNGRB applicability assessment
  • CGD regulatory compliance review
  • technical regulation mapping
  • compliance gap assessment
  • review of regulatory documents
  • identification of applicable PNGRB requirements
  • support in understanding referenced standards
  • licence and approval advisory where separately required
  • ongoing regulatory update support
  • compliance documentation assistance

For businesses dealing with multiple technical standards, regulatory compliance services can help connect the legal requirement with the engineering and operational documents already being used internally.

Corpseed does not replace the role of competent engineers, statutory authorities, or technical inspection bodies. Its role is to support businesses in understanding the applicable regulatory framework and organising compliance requirements correctly.

Key Takeaways

The PNGRB CGD Amendment Regulations 2026 change selected technical and safety requirements under the existing City Gas Distribution framework.

The main points businesses should remember are:

  • GI pipe use up to the consumer meter or meter control valve has been clarified.
  • Copper use before the consumer meter is restricted to the kitchen in the stated provision.
  • MLC pipe must meet ISO 17484-1 or IS 17544 and may also require compliance with PNGRB installation guidelines.
  • PE pipe cannot be used for above-ground gas piping unless specifically permitted.
  • Steel-reinforced rubber hose for meter-to-appliance connection must conform to IS 9573 Part 2.
  • DPRS/IPRS installations must maintain at least 2 metres between the enclosure and the permanent wall of the nearest building or structure.
  • Existing LPG manifold pipeline systems may be used for PNG supply in housing societies or residential complexes subject to relevant PNGRB guidelines.
  • Previously squeezed thermoplastic pipe locations must be marked.
  • The same reopened point cannot be squeezed again.
  • Consecutive squeeze-off locations must be at least 1 metre apart.
  • The notification does not expressly provide a separate transition period or new fee schedule.