Greenhouse Gas Emission Intensity Amendment Rules 2026
Quick note
Below is the official summary and the reference document preview. Use βOpen PDFβ for full screen view.
Schedule a Call Back
Summary
The Ministry of Environment, Forest and Climate Change (MoEFCC) has issued the Greenhouse Gases Emission Intensity Target (Amendment) Rules, 2026 through G.S.R. 794(E). The amendment replaces the existing entries in the Second Schedule for two sectors: Petroleum Refinery and Textile.
This is not a new carbon market law, nor does it bring these two sectors under the framework for the first time. Petroleum refineries, and textile units were already included through an earlier January 2026 amendment. The September 2026 amendment substitutes their existing scheduled entries with revised tables.
The change is especially relevant to the specifically named obligated entities. The revised schedule covers 21 petroleum refinery units and 173 textile units. Businesses should check the exact plant name, registration number, baseline data and applicable 2026-27 target rather than relying only on their sector or corporate name.
There is also an important date distinction. G.S.R. 794(E) carries a notification date of 7 September 2026, the Gazette issue is dated 9 September 2026, while the official eGazette records the publication date as 21 September 2026. Since Rule 1(ii) states that the amendment comes into force on the date of publication in the Official Gazette, the commencement date is 21 September 2026.
Notification at a Glance
| Particular | Verified Details |
| Issuing Authority | Ministry of Environment, Forest and Climate Change |
| Notification | Greenhouse Gases Emission Intensity Target (Amendment) Rules, 2026 |
| Notification Number | G.S.R. 794(E) |
| Notification Date | 7 September 2026 |
| Gazette Issue Date | 9 September 2026 |
| eGazette Publication Date | 21 September 2026 |
| Effective Date | 21 September 2026 |
| Gazette ID | CG-DL-E-21092026-276352 |
| Principal Rules | Greenhouse Gases Emission Intensity Target Rules, 2025 |
| Principal Notification | G.S.R. 739(E), dated 8 October 2025 |
| Earlier Relevant Amendment | G.S.R. 25(E), dated 13 January 2026 |
| Schedule Amended | Second Schedule |
| Sectors Revised | Petroleum Refinery and Textile |
| Petroleum Refinery Units Listed | 21 |
| Textile Units Listed | 173 |
| Baseline Year | 2023-24 |
| Target Column for 2025-26 | Shown as βββ in substituted Petroleum Refinery and Textile tables |
| Numerical Target Provided | Compliance Year 2026-27 |
| Governing Framework | Carbon Credit Trading Scheme, 2023 |
| Main Legal Basis for Amendment | Sections 3, 6 and 25 of the Environment (Protection) Act, 1986 |
The notification itself is dated 7 September, but the effective date should not be confused with that date. The official eGazette database identifies 21 September 2026 as the publication date, and the amendment expressly links commencement to Gazette publication.
What Exactly Has Changed Under G.S.R. 794(E)?
The most important point is simple: MoEFCC has substituted the existing Petroleum Refinery and Textile entries in the Second Schedule of the Greenhouse Gases Emission Intensity Target Rules, 2025.
The amendment does not rewrite the entire carbon-credit compliance mechanism. It changes the scheduled entries that identify the affected refinery and textile units and their relevant baseline and target data.
Rule 2 specifically provides for substitution of the existing Petroleum Refinery table, followed by substitution of the Textile table.
The visible change in the target columns
Under the January 2026 amendment, G.S.R. 25(E), the Second Schedule contained numerical targets for both 2025-26 and 2026-27. It also stated that the 2025-26 targets in the Second Schedule had been worked out on a pro-rata basis for January to March 2026.
In G.S.R. 794(E), the substituted Petroleum Refinery and Textile tables display a dash under the 2025-26 target column, while numerical figures continue to appear for 2026-27.
This change should be described carefully. The notification does not expressly define the dash as an βexemption,β βwaiverβ or βzero target.β Therefore, it is safer to state that the substituted schedule does not display a numerical 2025-26 target for these entries rather than assigning a legal meaning that the amendment itself does not state.
Old vs New Position
| Compliance Area | January 2026 Position | September 2026 Position | Practical Meaning |
| Second Schedule | G.S.R. 25(E) inserted entries for additional sectors | G.S.R. 794(E) substitutes Petroleum Refinery and Textile entries | Current businesses should use the substituted entries |
| Petroleum Refinery | Included in Second Schedule | Entire sector table substituted | Unit details and current target should be checked again |
| Textile | Included in Second Schedule | Entire sector table substituted | Textile units should use the current table |
| 2025-26 Target Column | Numerical pro-rata targets appeared | βββ appears against substituted refinery and textile entries | Do not continue using old 2025-26 figures without checking the current legal position |
| 2026-27 Target Column | Numerical targets appeared | Numerical targets appear in substituted schedule | Current unit-specific figure should be taken from G.S.R. 794(E) |
| Secondary Aluminium | Included by G.S.R. 25(E) | Not substituted by this amendment | G.S.R. 794(E) is not a general revision of every Second Schedule sector |
| Petrochemical | Included by G.S.R. 25(E) | Not substituted by this amendment | Existing entries are not replaced by this notification |
The amendment replaces the whole relevant tables, so businesses should avoid selectively carrying forward data from the January notification. The safer approach is to match their registration number against G.S.R. 794(E) and use the current scheduled information.
Regulatory Framework Behind the Amendment
The 2026 amendment sits within a wider carbon compliance structure. Understanding that structure helps explain why entity-specific intensity targets matter.
1. Carbon Credit Trading Scheme, 2023
The Central Government notified the Carbon Credit Trading Scheme, 2023, through S.O. 2825(E), dated 28 June 2023, using powers under clause (w) of Section 14 of the Energy Conservation Act, 2001. The scheme establishes the framework for India's carbon credit market.
A carbon credit under the scheme represents one tonne of carbon dioxide equivalent in terms of reduction, removal or avoidance of greenhouse gas emissions.
2. Greenhouse Gases Emission Intensity Target Rules, 2025
MoEFCC subsequently notified the Greenhouse Gases Emission Intensity Target Rules, 2025 through G.S.R. 739(E).
These rules set the legal framework for entity-level GHG emission intensity targets. They define a compliance year as the relevant financial year specified in the schedule and describe GHG emission intensity targets in terms of tonnes of carbon dioxide equivalent per equivalent output or product.
The original schedule covered Aluminium, Cement, Chlor-alkali and Pulp and Paper.
3. January 2026 Amendment
G.S.R. 25(E), dated 13 January 2026, expanded the scheduled framework to additional sectors, including:
- Secondary Aluminium
- Petroleum Refinery
- Petrochemical
- Textile
It inserted the Second Schedule containing entity-specific baseline and target information.
4. September 2026 Amendment
G.S.R. 794(E) does not introduce another group of sectors. Instead, it replaces the existing Second Schedule entries for Petroleum Refinery and Textile.
Regulatory Timeline
| Date | Regulatory Development | Why It Matters |
| 28 June 2023 | Carbon Credit Trading Scheme, 2023 notified through S.O. 2825(E) | Created the wider carbon-credit trading framework |
| 8 October 2025 | G.S.R. 739(E) issued | Greenhouse Gases Emission Intensity Target Rules, 2025 notified |
| 13 January 2026 | G.S.R. 25(E) issued | Second Schedule introduced for additional sectors including refinery and textile |
| 7 September 2026 | G.S.R. 794(E) notification dated | Amendment signed/notified by MoEFCC |
| 9 September 2026 | Gazette issue date | Gazette carries issue No. 726 |
| 21 September 2026 | Official eGazette publication date | Amendment comes into force on publication |
The date that matters most for commencement is 21 September 2026 because the amendment says it comes into force on publication and the official eGazette records that date as the publication date.
Why Were the Petroleum Refinery and Textile Entries Substituted?
G.S.R. 794(E) clearly says that the existing entries notified through G.S.R. 25(E) under Petroleum Refinery and Textile are to be substituted.
What it does not provide is a detailed technical explanation for why each figure or entry needed replacement.
Therefore, it would be inaccurate to say that the revision was issued because:
- companies could not meet their targets,
- the Government granted relief to the sectors,
- previous calculations were found wrong, or
- the industry sought a compliance extension.
None of these reasons is expressly stated in G.S.R. 794(E).
What can be stated with certainty is that the Central Government decided to replace the existing scheduled entries and that the substituted tables are now the relevant source for the affected entities.
Scope and Applicability
This amendment does not apply to every petroleum refinery or textile manufacturer in India.
It applies specifically to the obligated entities listed in the Second Schedule.
Petroleum Refinery Sector
The substituted refinery table contains 21 obligated entities. The final refinery entry is Reliance Industries Ltd's Jamnagar SEZ unit at serial number 21 after which the notification begins the Textile table.
For each refinery, the schedule contains information such as:
- unit name and location,
- registration number,
- baseline crude throughput for 2023-24,
- NRGF factor,
- baseline GHG emission intensity,
- 2025-26 column, and
- 2026-27 target.
Textile Sector
The Textile schedule covers 173 obligated entities.
The list ends with registration numbers TXTOE168GJ to TXTOE173GJ. Mafatlal Industries Limited's Textile Division appears at serial number 173.
A textile company should therefore not assume applicability simply because it operates a spinning, processing, fibre or integrated textile facility. The exact scheduled plant and registration number need to be checked.
Textile Sub-Sectors Covered Under the Revised Schedule
The 173 textile entries are divided into four sub-sectors.
| Textile Sub-Sector | Serial Number Range | Listed Entities |
| Spinning | 1-60 | 60 |
| Processing | 61-94 | 34 |
| Fibre | 95-127 | 33 |
| Composite | 128-173 | 46 |
| Total | 1-173 | 173 |
The Gazette marks Spinning from the beginning of the Textile schedule, moves to Processing from serial number 61, Fibre from serial number 95 and Composite from serial number 128.
These numbers describe the obligated entities in the regulatory schedule. They should not be presented as the number of textile businesses operating in India.
What Is a GHG Emission Intensity Target?
GHG emission intensity is different from absolute greenhouse gas emissions.
Absolute emissions tell a business how much greenhouse gas it has emitted in total.
Emission intensity relates emissions to a defined amount of production or output.
For example, two factories may have different total emissions simply because one produces much more than the other. An intensity-based system compares emissions with production/output, helping measure the carbon intensity of the manufacturing activity.
The principal 2025 Rules define GHG emission intensity targets in terms of tCO2e per equivalent output or product.
That is why the Gazette contains both production-related baseline data and an emission-intensity figure for individual obligated entities.
Understanding the 2023-24 Baseline
The revised schedules use 2023-24 as the baseline year.
The baseline gives the regulatory framework a reference point against which the entity-specific target is structured.
For a listed business, three pieces of information should not be mixed up:
- Baseline production/output tells the regulator what production basis is being used.
- Baseline GHG emission intensity records the starting emission-intensity position.
- Compliance-year target specifies the intensity level applicable to the relevant compliance year.
An internal sustainability report that uses a different organisational boundary, production unit or calculation method should not automatically be treated as equivalent to the regulatory baseline. The applicable methodology under the Carbon Credit Trading Scheme must be followed.
How to Read the Petroleum Refinery Table
The refinery schedule is different from the textile schedule because its production and intensity basis is refinery-specific.
Obligated Entity
Each row identifies a particular refinery, not simply a corporate group.
For example, one oil company can have several separately listed refineries, each with its own location, registration number and target.
Registration Number
The registration number is particularly useful when matching a plant to the schedule. The refinery registrations follow identifiers such as:
- REFOE001MP
- REFOE002KL
- REFOE003MH
Businesses should use the registration number together with the plant name rather than relying only on the company name.
Baseline Crude Throughput
The Gazette records baseline crude throughput for 2023-24 in MBBLS.
NRGF
A separate NRGF factor is included in the refinery table. G.S.R. 794(E) does not itself expand or separately define NRGF in the amendment text. Its technical use should therefore be read with the applicable BEE methodology or detailed procedure rather than guessed from the abbreviation.
Baseline GHG Emission Intensity
The refinery baseline intensity is expressed using the basis shown in the Gazette:
tCO2 equivalent/MBBLS/NRGF
Compliance-Year Target
The substituted refinery schedule shows a dash under 2025-26 and a numerical target under 2026-27.
For example, the Bina Refinery entry shows a 2023-24 baseline GHG emission intensity of 6.6553 and a 2026-27 target of 6.3846 on the scheduled basis.
This illustrates why unit-level checking matters. A target applicable to one refinery should never be copied across to another plant.
What Does the βββ Under 2025-26 Mean?
This is one of the most important interpretation points in the new notification. The current substituted tables show a dash in the 2025-26 target column for the Petroleum Refinery and Textile entries.
However, G.S.R. 794(E) does not include a separate explanation saying that the dash means:
- zero target,
- exemption,
- waiver,
- target achieved,
- cancellation of every related obligation, or
- extension to another date.
Therefore, the safest description is:
The substituted schedule does not specify a numerical 2025-26 GHG emission intensity target for these entries.
That is different from saying that the Government has expressly granted a "waiver." Unless MoEFCC or BEE issues an official clarification giving the dash a specific legal meaning, businesses should avoid using broader language.
How to Read the Textile Schedule
For textile entities, the schedule follows a different production basis.
It contains:
- unit name, address and state,
- registration number,
- baseline equivalent major product output for 2023-24,
- baseline GHG emission intensity,
- 2025-26 target column, and
- 2026-27 target.
The production value is shown in tonnes, while the intensity basis is expressed as:
tCO2 equivalent per tonne of equivalent product
The use of an equivalent-product basis matters because different textile plants may have very different products, operating processes and production mixes.
A textile business should therefore not compare its raw production tonnage directly with another plant's regulatory position without first understanding the applicable equivalent-product methodology.
Is Every Petroleum Refinery or Textile Business Covered?
No. The amendment uses an entity-specific scheduled approach. A business should first check whether its particular facility appears in the Second Schedule.
A useful applicability check is:
- Match the exact unit or plant name.
- Confirm the address and state.
- Match the registration number.
- Identify the sector or textile sub-sector.
- Check the baseline production/output.
- Check the baseline GHG intensity.
- Record the applicable 2026-27 target.
A company operating several plants should repeat this review for each plant. One registration or target cannot automatically be assumed to cover the group's other facilities.
Does G.S.R. 794(E) Create a New Registration Requirement?
The amendment itself does not create a fresh registration process merely because registration numbers appear in its tables.
However, the wider Greenhouse Gases Emission Intensity Target Rules require obligated entities to register on the portal under the Indian Carbon Market Framework and to submit documents in accordance with the detailed procedure under the Carbon Credit Trading Scheme.
This distinction matters.
G.S.R. 794(E) changes the schedule. The underlying registration and compliance duties flow from the principal rules and the wider Carbon Credit Trading Scheme framework.
Compliance Requirements for Obligated Entities
The September amendment should be read together with the principal Greenhouse Gases Emission Intensity Target Rules, 2025.
Under those rules, an obligated entity is required to achieve the applicable scheduled target, comply with the relevant Carbon Credit Trading Scheme requirements, register on the Indian Carbon Market portal and make the required submissions under the detailed procedure.
Meeting the applicable GEI target
For the relevant compliance year, the business needs to compare its achieved greenhouse gas emission intensity against the target assigned to that specific obligated entity.
Indian Carbon Market registration
The principal rules require obligated entities to register on the relevant Indian Carbon Market portal.
G.S.R. 794(E) itself does not establish a new portal or a separate September 2026 registration process.
Document submission
The principal rules require documents to be submitted in accordance with the detailed procedure.
Businesses therefore need to keep the schedule, detailed procedure and subsequent BEE instructions together rather than reading only the target table.
Carbon credit certificates for shortfall
Where the achieved GEI does not meet the target, the principal rules provide for carbon credit certificates to be purchased to cover the shortfall.
Where an entity performs better than its target, the framework contains provisions for issuance of carbon credit certificates, subject to the applicable rules and detailed procedure.
How Carbon Credit Certificates Connect with the Target
The principal rules provide a mathematical link between achieved performance and carbon credit certificates.
For issuance, the framework works broadly on:
GEI Target- GEI Achieved Γ Equivalent Product Output
Where achieved intensity is lower than the applicable target, the result can form the basis for the number of carbon credit certificates to be issued.
For a shortfall, the calculation operates in the other direction:
GEI Achieved- GEI Target Γ Equivalent Product Output
The resulting amount determines the carbon credit certificates to be purchased for compliance, subject to the detailed procedure.
This is why accurate emissions and production data are not merely reporting numbers. They can directly affect an obligated entity's carbon-credit position.
Practical Compliance Roadmap for Listed Businesses
1. Confirm the exact scheduled facility
Begin with the company name, then check the location, and registration number too. All three details should match the scheduled facility.
2. Update old internal target references
Check whether your internal compliance records still use the January 2026 Petroleum Refinery or Textile schedule. If they do, update those records using G.S.R. 794(E). This may include:
- internal compliance trackers,
- ESG and sustainability working papers,
- plant-level carbon dashboards,
- management reports,
- consultant working files, and
- target-monitoring spreadsheets.
3. Record the current 2026-27 target
Enter the target linked to the correct registration number. Do not use the target listed for another plant, or rely on an industry-wide average.
4. Check the 2025-26 column carefully
The current table shows a dash in this column. Do not carry forward the January numerical value without first checking the applicable legal, and regulatory position.
Also, do not treat the dash as a waiver unless an official clarification confirms this.
5. Match production and emissions data
Check the plant's production, and emissions records against the boundary, and production basis prescribed under the applicable methodology. Any difference in the basis used can affect the figures reported.
6. Check portal and document requirements
Review the latest BEE detailed procedure and Indian Carbon Market instructions for the requirements relating to registration, monitoring, reporting, verification and submission.
7. Estimate the compliance position
Businesses should assess whether current operational performance is moving towards the relevant 2026-27 target.
8. Maintain supporting records
Production, fuel, energy, process and GHG information used for regulatory calculations should be internally consistent and traceable.
Data Businesses Should Review Immediately
The first internal review should bring together the scheduled regulatory information and the plant's own compliance data.
| Data Point | Why It Matters |
| Scheduled unit name | Confirms correct facility |
| Registration number | Helps avoid applying another plant's target |
| Plant location | Confirms identity where company has multiple units |
| Relevant sector/sub-sector | Determines correct schedule position |
| 2023-24 baseline output | Provides production reference |
| Baseline GEI | Shows starting intensity position |
| NRGF, where applicable | Relevant to petroleum refinery calculation basis |
| 2026-27 GEI target | Current numerical target in substituted table |
| Current production data | Needed to assess actual performance |
| Current GHG data | Needed for achieved GEI assessment |
| Supporting records | Helps with reporting and verification requirements |
For refinery groups and large textile companies with multiple plants, this review should be done at the registration-number level, not only at corporate level.
Impact on Petroleum Refineries
For the 21 listed refineries, the amendment makes the current schedule the starting point for carbon-target planning.
Plant-level target control
Large oil companies often operate more than one refinery. Each scheduled unit has its own registration and target.
Compliance teams therefore need a plant-wise target register rather than one group-level carbon number.
Throughput data becomes central
Because the refinery table uses crude throughput along with the refinery-specific intensity basis, data maintained by operations, sustainability and compliance teams needs to reconcile.
Differences between operational reports and the data used for regulatory calculations may create problems later during reporting or verification.
Energy and emissions planning
A lower 2026-27 target means that operational teams need visibility over whether current efficiency and decarbonisation measures are sufficient to move the refinery's achieved intensity towards the prescribed level.
The amendment itself does not order a particular technology investment. Each business remains responsible for deciding how it will manage its compliance position within the applicable framework.
Impact on Textile Businesses
The textile schedule is much larger and more diverse, with 173 obligated entities spread across four sub-sectors.
1. Spinning units
With 60 scheduled entries, spinning forms the largest single group before the Composite category is considered.
Businesses should match the actual unit, registration and equivalent-product basis before calculating progress against the target.
2. Processing units
The schedule contains 34 processing entries.
Energy-intensive activities such as dyeing, finishing or other processing operations may affect the plant's emissions profile, but the regulation should be applied through the official GEI methodology rather than a generic industry assumption.
3. Fibre units
The 33 Fibre entries have their own baseline production and intensity numbers.
For such units, consistency between manufacturing data and emissions calculations is particularly important because the regulatory comparison is entity-specific.
4. Composite textile units
There are 46 Composite entries.
Integrated facilities may involve several processes within the same operation. Compliance teams need to ensure that the production and emissions boundary used internally corresponds with the methodology applicable to the registered obligated entity.
Business Impact Matrix
| Stakeholder | Immediate Impact | Main Concern | Priority Action |
| Listed Petroleum Refineries | Revised schedule now applies | Correct plant target and calculation basis | Re-check registration and target |
| Textile Spinning Units | Revised table applies | Correct output and intensity data | Match unit against schedule |
| Textile Processing Units | Updated scheduled position | Energy and emissions data consistency | Review compliance dataset |
| Textile Fibre Units | Revised entity-level targets | Equivalent-product calculation | Verify methodology |
| Composite Textile Units | Plant-specific target control | Multiple manufacturing processes | Confirm compliance boundary |
| Environment/Sustainability Teams | New schedule must enter internal systems | Old figures remaining in reports | Update trackers and dashboards |
| Operations/Energy Teams | Performance must be assessed against target | Production and energy data alignment | Review abatement measures |
| Compliance/Legal Teams | Current schedule supersedes relevant earlier entries | Wrong interpretation of 2025-26 dash | Maintain current legal register |
Compliance Risks Businesses Should Avoid
One of the easiest mistakes is using a company-level approach where the regulation is plant-specific. A corporate group may have several units in the schedule, and each needs to be checked separately.
Another risk is continuing to use the January 2026 numerical 2025-26 targets without noticing that the substituted table now displays a dash for that year.
Businesses should also avoid treating the dash as "zero." Zero is a numerical target, a dash is not.
Other areas that deserve attention include incorrect registration-number mapping, mixing total emissions with emission intensity, using the wrong textile sub-sector, relying on an internal calculation method that does not match the prescribed procedure, or using another facility's production/output basis.
Risks and Consequences of Non-Compliance
G.S.R. 794(E) does not create a separate penalty mechanism. The consequences sit in the principal Greenhouse Gases Emission Intensity Target Rules, 2025.
Under those rules, if an obligated entity fails to comply with the responsibilities prescribed under Rule 4, the Central Pollution Control Board (CPCB) may impose environmental compensation for the shortfall.
The rules provide that the compensation is equal to twice the average price at which carbon credit certificates are traded during the relevant compliance-year trading cycle, with the average price determined by BEE. The affected entity must first be given a reasonable opportunity of being heard. Environmental compensation is payable within 90 days of the order.
This consequence should not be confused with something newly introduced by G.S.R. 794(E). It comes from the existing principal rules.
Challenges and Cost Implications
The amendment does not prescribe a fixed compliance cost for affected businesses.
The actual burden will depend on each facility's current emissions performance, data systems and the level of improvement required to meet the target.
- Data-management cost: Businesses may need better systems for bringing production, fuel, energy and emissions data into one consistent regulatory dataset.
- Measurement and verification readiness: Where the wider framework requires verification, poor documentation can become a larger problem than the emissions calculation itself. Businesses need to retain enough evidence to support the figures being reported.
- Operational adjustments: Facilities that are materially above their target pathway may need to examine process efficiency, energy use, fuel mix or other abatement options.
- Such investments are business decisions, the amendment does not prescribe one technology solution.
- Carbon-credit exposure: Where the applicable rules result in a carbon-credit shortfall, purchasing certificates may add a compliance cost. Conversely, performance better than the target can have a different carbon-credit outcome under the scheme.
The actual value cannot be estimated merely from the target table because production and achieved GEI are also required.
Benefits of Early Compliance Planning
Early review can reduce uncertainty around the regulation even before any major capital decision is taken.
For listed facilities, it can help management identify whether the correct target has been entered into internal systems, whether production and emissions information reconcile, and whether the plant appears to be moving towards its 2026-27 requirement.
It can also give the business more time to identify data gaps, assign internal responsibilities and assess whether operational improvements are commercially preferable to relying on carbon-credit purchases for a future shortfall.
These are planning benefits rather than guaranteed financial savings.
Business Opportunities Around Carbon Compliance
The wider compliance mechanism is also creating demand for specialised support around carbon management.
Affected industries may increasingly need assistance with GHG accounting, carbon-data systems, process-efficiency assessments, verification readiness, energy-management projects and regulatory interpretation.
Technology providers working on energy efficiency, emissions measurement and industrial decarbonisation may also find opportunities as obligated facilities examine how to improve their intensity position.
However, neither G.S.R. 794(E) nor the attached Gazette provides a market-size or revenue estimate, so commercial opportunity should not be presented using unsupported numbers.
Regulatory Burden vs Carbon-Efficiency Opportunity
For affected facilities, both sides need to be considered.
From a compliance perspective, entity-level targets add another layer of data, reporting and management responsibility. A refinery or textile unit cannot rely only on general ESG reporting. The regulatory calculation has its own defined schedule and methodology.
From an operational perspective, the same system can give management a clearer measure of how emissions change relative to production. That information may support decisions around energy efficiency, process optimisation and longer-term decarbonisation.
Whether the result is primarily a cost or an operational opportunity will differ from facility to facility. The notification itself does not make that commercial assessment.
What Businesses Should Do Next
Businesses appearing in the revised schedule should make the new Gazette part of their active compliance records rather than treating it as a general environmental news item.
The immediate priorities are to confirm the plant and registration number, capture the correct 2026-27 target, replace superseded internal schedule data, review the 2025-26 dash carefully, reconcile emissions and production data, and check the latest BEE compliance procedure and portal requirements.
Management should also make responsibilities clear between operations, energy, sustainability, finance and legal/compliance teams. Carbon compliance becomes difficult when production data sits with one department and emissions information with another.
How Corpseed Can Help?
For a listed refinery or textile facility, the first challenge is often determining what the Gazette means for that particular plant. Corpseed's environmental compliance services can support businesses in turning the schedule into a practical compliance review.
Applicability Assessment
Corpseed can assist in matching the business's facility name, location, registration number and relevant sector or textile sub-sector with the revised Second Schedule.
GHG Target Review
Support can be provided in identifying the correct baseline and current target against the registered facility and reviewing whether older internal target references need to be replaced.
Regulatory Interpretation
Corpseed can help businesses understand how G.S.R. 794(E) connects with the Greenhouse Gases Emission Intensity Target Rules, 2025, the Carbon Credit Trading Scheme, 2023 and relevant BEE procedures.
Environmental Compliance Gap Assessment
A compliance gap assessment can review whether the business has the required production, energy, emissions and supporting information available for its regulatory compliance work.
GHG Data and Documentation Review
Corpseed can support the organisation and review of relevant compliance records so that production and emissions information can be traced and reconciled.
Carbon Compliance Readiness
Businesses can also obtain support in understanding their carbon compliance position, internal responsibilities and upcoming actions under the applicable Indian Carbon Market framework.
Ongoing Regulatory Compliance Support
The carbon-market framework continues to operate through interconnected rules, schedules and detailed procedures. Corpseed can support businesses in tracking relevant changes and evaluating their effect on existing compliance systems.
Businesses covered by the revised schedule can use Corpseed's environmental compliance services and regulatory compliance services to review applicability, identify compliance gaps and prepare their internal records for the applicable carbon-market requirements.
Key Takeaways
- MoEFCC has issued G.S.R. 794(E) to amend the Greenhouse Gases Emission Intensity Target Rules, 2025.
- The amendment substitutes the Second Schedule entries for Petroleum Refinery and Textile.
- The notification is dated 7 September 2026, while the official eGazette records publication on 21 September 2026. Because commencement is linked to publication, 21 September 2026 is the effective date.
- The substituted schedule covers 21 petroleum refinery units and 173 textile units.
- The 173 textile entries are divided into Spinning, Processing, Fibre and Composite sub-sectors.
- The baseline year remains 2023-24.
- The revised Petroleum Refinery and Textile tables show a dash for 2025-26 and numerical targets for 2026-27.
- The notification does not expressly define the dash as a waiver, exemption or zero target.
- Applicability is plant- and registration-specific, every refinery or textile business should not automatically be treated as an obligated entity.
- Wider duties relating to target achievement, Indian Carbon Market registration, document submission and carbon credit certificates continue to arise under the principal rules.